Stop Being the Bank for Everybody: A Heavy Civil CFO's Cash Playbook with Joseph Patti
Joseph Patti in conversation with host Rishi Srivastava

Summary
"Why are we the bank for everybody?" That question sits behind every turnaround Joseph Patti has led.
Joseph is CFO of Restani Construction Corp., a New York City heavy civil contractor. He is a CPA and CCIFP who has worked in construction finance since 1990, and a longtime CFMA leader, including past president of the New Jersey Chapter. In this episode he shares the cash, forecasting, and job tracking habits he brings to every contractor he joins, and how his team now uses AI on top of Sage 300 and HCSS to know how each job did every single day.
In this episode:
- How collecting material deposits up front helped take a flooring contractor from $10 million owed on its credit line to about $15 million in the bank
- The turnaround levers at McLaren Engineering: weekly collection meetings, a bank-to-book 13-week cash flow, 85 to 90 percent utilization targets, and estimates to complete owned by project managers
- Why borrowing at 18 percent on a 15 percent margin job means you are going backwards
- What makes NYC agency work different: low-bid competition, utility conflicts, weather, and claims
- Running the company "like a candy store": daily cost versus daily billable quantities, with AI pulling Sage 300 and HCSS data into one place
- Unit price jobs: why daily quantity tracking makes your numbers "bulletproof," and why quantity you give up never comes back
- Substituting bonds for cash retainage, and the $200,000 to $250,000 a year in interest income on a $5 million retainage position
- The 5 percent mobilization payment trap and the race to the bottom on bids
- Why the current ratio can mislead, and why underbillings and the financial statement notes deserve more attention
- How CFMA's Financial Benchmarker avoids double counting contractor and CPA firm data
- What a first-year construction CFO should do this month
Transcript
9,146 words · about 61 minutes. Transcribed from the recording, so expect the odd mis-heard word.
Today our guest is Joseph Patti. Joseph, welcome.
Thank you. I'm happy to be here.
First section is journey into construction finance. Take us back to the beginning. How did you end up in construction finance? Specifically, and what was it about contractors that pulled you in over any other industry?
I I wish I could say it was really a a glamorous thing that I I really wanted to get involved with building buildings and and digging holes and and
Mm-hmm.
you know, building the subways and that type of thing, but it it really wasn't. when i even even in university I went to NYU and and I was there in the eighties and I was a I was a finance major. I wanted to work on Wall Street, I wanted to be Gordon Gecko. And
And the when I was graduating, the the market was not really great. And fortunately, like I had a degree in finance, but one of my professors there at NYU convinced me that I I had a knack for accounting, so I he said take it up as a second major. So I did that, and fortunately I did because when I was graduating they froze hiring at the brokerage houses, so I ended up going into accounting, went into public accounting first.
there for a few years and then there was a recession so I ended up leaving and the two companies that were interested in me were both construction companies because I had done
Hmm.
you know like managerial accounting I had managerial clients so I knew like percent complete stuff and and that type of thing so it made that it made them interested in me and I got into construction that way. And then after that I
You know, I grew in the industry where, you know, I decided to go back, get my CPA, then I went back for my MBA. And lastly when the C C IF P came out in two thousand four, I I wasn't
Mm.
back 'cause I wanted to be known as a an industry expert.
Mm.
and I'm happy I did that 'cause it it really helped develop me a as a a more well rounded construction professional. But I love the industry now. I mean I've been in it since nineteen ninety and
different firms and I've learned
nothing else I'd rather do now.
Yeah. Constructions it takes you in.
Yes, for sure.
You've built a real specialty in turning around financially distressed construction firms. Walk us through the McLaren engineering story. You helped take the share price up 25% before the ESOP acquisition. What was broken when you walked in, and what were the first two or three levers you pulled?
Before before talking about McLaren, prior to that I worked at a flooring company and and it was before COVID and before COVID we had owed like, you know, ten million dollars to our credit line and and and structurally we were behind. We were we were doing flooring work where we were paying for the materials beforehand and and then using our own credit line to pay for it and then
building the job and being behind in in payments until you finally catch up. But one thing I suggested to the owner was listen, we should get deposits for all our materials and and use the the you know, the client's money to be able to do our purchases and
Right before COVID it was kinda sinking in and then when COVID hit it was like, hey, we're we're gonna be cash crunched and we're already cash crunch. So let's start doing that as a company and then doing other things and making sure that we don't lay out money before we get paid. And we turned that that ten million dollar deficit around to where when I left the company we had like
fifteen million dollars in the bank. So just the the shift in mindset for for money and and thinking about hey we gotta ask to get paid before you know we do stuff, that's really important. And and going into McLaren, you know, look looking at how they were doing business and not getting deposits was one thing. But it was more about looking at their receivables and they they didn't have a lot of accountability or
leaders were not actively pursuing their collections and and that type of thing. So one of the first things I I did there was I put in weekly collection meetings to to bring them back up to where we could pay bills. so that was just the first thing to do there. you
Mm-hmm.
know that we had big cash flow problems where we were paying people before we got paid so it became more of hey, you know
Why why are we the bank for everybody? So we need to figure out how to not do that and and you know like kind of spread the pain as they say, right? If you owe people
Yeah, yeah.
money and you're owed money, like hey, like don't don't lay out the money unless you really have to. You know. so you know, collection they were lacking clear direction and and how to follow up and holding I was holding you know
Vision Heads accountable for getting their money monthly and and and weekly and and making calls to clients to get paid. Other things we were doing were a 13-week cash flow where they
Mm-hmm.
it using it bank to book, where you know, like looking at the bank, you know how much money you have, but it doesn't say how many checks you have outstanding and that type of thing. So
better planning where we were doing bank to book weekly and and th thirteen weeks ahead to know, hey, all right, we can pay these things week six, we can pay these things week ten and and just have a better plan and not be surprised like, crap, we can't make payroll this week.
Yeah, yeah.
So that was when I when I joined the firm the the president of the company, this guy Jeremy, really great guy and very astute man.
He he knew he needed someone that can kind of force these issues through the the vision heads and make sure that we
accountable. Other things that we did was we eliminated overtime because you know there was a lot of unnecessary overtime and and then looking at the budgets
U using the backlog for each division to figure out what their real headcount should be and doing utilizations for everybody and making sure that everyone was at least eighty-five to ninety percent utilized and billing clients. Those those were things that were real hot buttons to to push to to make sure that we we had our
thing about is it it it started sticking with them where you know the division heads got a little competitive in terms of collections and you know no one wanted to be the one who had the most outstanding money and and that type of thing and and it was all brought up in the and just being more regimented that that kind of stuff was so important to to the turnaround and
Lastly, what the one thing they were doing was they were managing their estimates to complete based on like utilization rates and that type of thing as opposed to looking at every job and saying, hey, what do we have left to do? You know, what phase are we in? Would it be design development, construction documents, that type of thing, leaving money to finish and and knowing what their real margins were was really important because
otherwise you were flying in the dark and
Mm-hmm.
or trying to hit a target. So you doing real percent completes on the jobs instead of just me doing it and then giving it to the account and and not asking for information from the project managers, that was the way it was done in the past. So getting people to be responsible to make their estimates to complete was so important as well.
Actually, we we just built an MCP connector, and what it does is it connects directly to ERP like foundation. So one
Yeah.
CFO it was taking him like two to three hours to get paid when paid reports out of the ERPs. It's tough, right? You gotta maneuver through so much stuff, and this connector does it in like a minute. So you just write, give
That's great. Yeah.
me my pay when paid, it goes through and just navigates the ERP and gets you the report in a minute.
Yeah,
we we do that internally too, where we we use our system to say, All right, a requisition it it Restani, a requisition for a million and a half goes to a client and we know what subs and what material suppliers are tied to this requisition to know when we get paid, we're able to say, All right, like hit a button and say, All right, these vendors are are the ones that we have to pay to this requisition. It's kinda like
There there there's other products on the market that do that, but
Yeah, yeah.
we kinda develop Textura is the one that I was taking up. we
Hmm.
do that internally as well. It's important 'cause, you know, w the subs are asking when did you get paid because they know they're tied to it, you know.
Right, right. Yeah, the re reporting's getting it timely and accurate is so important.
Yes, hundred percent.
you are about six months into Restani now. What was the diagnosis when you arrived and what does quote unquote profitable and poised for growth actually look like from the inside today?
I'm I'm here ten months now, so we we we talked way back when but anyway that it's there's a lot of a lot of good stuff going on here. When when
Mm-hmm.
I first joined the company we were you know pretty cash poor and we were
pay some of our payables for us and then owing them the money.
paid a lot of interest over the the year prior to me being here. And the first thing that I targeted was you know to do a cash flow and to look to see when we can exit that relationship because the interest rates were really high. And
Yeah, yeah.
you know like let's say let's say a company job a job that you're working on is a
fifteen percent profit job. If you're borrowing at eighteen percent, you're going backwards. You know? And
Yeah.
there's a lot of companies that that are doing that now. I came from a company that was doing that.
They were going backwards and and it was something that that I couldn't help them with in the end. After after after being there for a few months, I was like, I don't see the way out of this. But
Ha ha ha.
but Restani was a company that really the reason for their their cash shortfall was we had one bad project that we're working on building a claim for. And it's enormous and the
the owners have put a lot of personal money back into the business, had have have sold real estate and and have done all the right things to bring the company back to becoming cash sufficient. the c the company right now is profitable but we're still working our way out of
cash shortfalls. By the end of the year we should be totally clear, which is great. You know, good planning and good good budgeting and and using forecasting and looking at at projects and saying, well what happened here? Why did we lose money? you know, we have a change. Put together a change order and go and collect some of this old debt, you know, so a lot of that stuff is is coming to fruition now, which is great.
Company culture wise, the the owners are very hands-on and they're great guys to work for. I I I I've never been happier working for for an owner. the some of the things I I've put in place. We we used to do a you know a 13-week cash flow, but the cash flow was done on a bank basis as opposed to bank to book. So you're not factoring in the checks that are coming in and and and
kind of surprise
Mm.
all of a sudden the bank number goes from two million dollars down to like five hundred thousand and you're like, no. You
Mm-hmm.
you have to you have to do that reconciliation. I I reconcile the bank account a couple of times a week, the the arm
coming and what w when we're getting paid for things, when I could pay subs and vendors and
things for for us is good forecasting and making people accountable for being able to forecast how much their jobs are gonna spend during pe in during each period, knowing what they're gonna bill and what what money's coming in and and doing estimates to complete monthly and and and getting into a flow where we're having these conversations with like
using the technology to make that easy because we use Sage three hundred, it's not really great for research and we use
Mm-hmm.
EBID and and and HCSS for tracking and that the information is is not easy to get out of and we're using AI to get that information together in one place to do analysis and it's it's become a a game changer for us.
Nice. The next section is running the finance function at a heavy civil shop. For listeners who only know commercial GCs are vertical work, paint a picture of the heavy civil world. NYC agencies, MTA, DOT. What makes financing this business fundamentally different from a contractor building offices or hospitals?
Well as far as New York City work
hospitals and and that type of work. the bidding for that that could be it it it might not be as competitive. It's extremely competitive bidding on these projects. You have the same five to ten contractors that are all hungry for work and these bids are are you know, lowest bidder for the most part. Sometimes they do design
Hmm.
build where they have a criteria for for picking the contractor, but for the most part the lowest price is is the pre the real determiner.
of of who gets to work, right? And and then dealing with the the engineers, the resident engineers and and the people at the agency is not always easy because they they all have a job to do and they wanna save save the agency money because it makes them look better and and and that type of thing. But
they they have to be fair as well. And and sometimes they're not and it's it's frustrating. That's why you end up going a claim and you know, it becomes contentious for change orders and that type of
The one thing that people don't think about when it comes down to doing work for these agencies is there's other parties involved, right? So when you're working in the street and you hit a conduit or you hit a sewer line or something like that, you have to deal with Con Edison here, or you deal with National Grid, or you're dealing with other people besides the the agency you're working for. So you have to negotiate with them in terms of
the delays they're causing or moving their their ducts and their and and that type of thing that they have to pay you as well. So you're negotiating with them, you're negotiating with the agency and it's important that you
you recapture the cost that you would spend to to do their work. And a lot of times that doesn't happen because unless you're tracking it really well. So I'll I'll get to that later when we we talk about how we're tracking stuff. But you know the utilities create delays, you know obstructions and sometimes you can't work and you you're basically standing there waiting for them to to give you an answer to to to what they want you to do
Mm-hmm.
hacked by weather because we're working outside, right? So last winter was terrible. I mean there were storms constantly and and you know we had a lot of people that we were carrying because we didn't think the weather would be so bad. So you know it's a little bit more of a plan going into this year. Hey, what how many people are we going to carry? What are they going to be working on? They're going to be working on stuff that's weather protected and and and that type of thing. And
key things that we we're getting better at is our relationship with the agencies. We realize how important it is to be to play nice in a sandbox because if you don't they can really kind of they they can take advantage of you and and hold you up hold your money up where you know it ends up your borrowing to continue doing business and it's a a frustrating thing. But so there's a lot of outside
things that impact your work that maybe in if you're doing building work it's not so bad. You know, but they have other issues like we're where multiple trades are working and and and but we don't really have
You are running Sage 300 plus HCSS heavy bed plus custom dashboards. Talk us through how you actually use that stack day to day. What are the two or three numbers you are looking at before 9 a.m.?
Well what I'm what I'm looking at before nine AM is is cash. Yeah, but
Mm.
and and having that information is is very important. and looking to see who who's asking for money this week.
Mm-hmm.
So those things are are vital. But
We're we're presently we're like I said, we're using Sage three hundred and we're using H C SS and we're gathering information daily from the field on the project, you know, with the daily quantities, daily timesheets and and what productions were done each day. So that information is looked at more
I I I ha I haven't built out my dashboard yet to the degree I need to for these things, but but I look in and and we have weekly quantity meetings on the jobs that we talk talk through how how we did this week and in terms of cost and obviously you wanna be you wanna spend less money than what you've made when when we're dealing with the owners. So
the AI information puts everything in one place where you can kinda look at it. Like I use it I use it ninety percent of the time versus ten percent where I'm in Sage. I'm in Sage making entries and and that type of thing, but for the most part I can get everything I need out of the the AI information where I can drill down and look at invoices. I can I can compare my income statement and and download
to to say why my variances are what they are unless
Hmm.
I can know what client paid me and I can look all that up and not have to go into to to Sage to do that. I can look at my AP aging the same way. So there's other stuff too. like the
Yeah.
Using the daily reports we t we tend to look at the company, the company production like a candy store, right? So when you own a candy store you're selling, you know, five bags of potato chips, three three snapples, that type of thing, and you know how much money it costs you to to to
money you you received at the end of the day for it so you you have your daily receipts we use our our system to figure that out how did we do today how much did our labor cost us our subs our material our equipment all that stuff versus how much money will be we be able to build a client in quantities we did that day so
Mm.
it's pretty it's pretty robust and
Right, right.
it's exciting because
a lot of times you you you don't know how you're doing until you do a snapshot in time and you're like, crap, we're really behind here. But we know we know daily how we're doing on each shot.
And it's like, all right,
Mm.
well what are we doing here that we're not making money? Well, can we change our crew sizes? Can we have you know this this crew work here because they're they're better at this, you know, like so it you do tinkering with stuff to to to improve upon your results because you have your results real time.
Yeah, so what AI tool are you using to look at these reports?
Well
it's it's a mixture of of Claude and Chat G P T and stuff but we we use multiple platforms for for AI because they're one's better than another in in in terms of tracking stuff. I'm not the expert at it. we have a CIO that does that stuff and
He's a real guru at it and he sits in on a lot of our meetings and when we talk about costs and projects and stuff like that. Because when when we ask a question, he can show us where to get the information and we can get the information ourselves. But but I'll sit in the meeting and Sal and Charlie will sit in the meeting and go, you know, it'd be nice if we were able to look at it in this way. And he'll take a note and then the next time we look at it, there it is the way it we ask for it. So it
We're improving this on the fly and and it's it's really cool, you know, to be able to track the information we are.
What's a metric the rest of the industry obsesses over that you think is overrated in heavy civil? And what should they be looking at instead?
Well, in our case, right, you look at our current ratio within the company and and it's it doesn't look so great. But part of the reason why is because we'll you know, some of the debt we took on is like intercompany debt. So that basically will in in increase decrease the current ratio. But if if
We owe money to one of the owners, other entities, i it it shouldn't affect the ratio. It it it does because of of calculation, but it we could resolve that like tomorrow without knowing it it's casting a bad light that it it it shouldn't be, right? So we had a discussion about that with with a potential partner on a job and
You know, I went back to them and explained, hey, you know, our ratios are if you back these idols out, this is where we really are. And they they understood that and and ended up them having them look at us in a more favorable light. but and and the key thing is if you're looking at financials, look at the notes. Because the notes explain why things are and
And sometimes it looks a little more draconian in the statement than the notes make it seem. Or it could be the opposite, to be honest, right? It it might look innocuous, but then you you look at the note and my god, there's this large claim they owe money here and and like one one key metric that I look at is our underbilling number.
Mm.
'Cause
Under billings are are indicative of potential issues, right? The the owners are not letting you bill and there's a reason why, right? There's something either unresolved with change orders, or you might have a claim, or lastly, you have a you you've overstated what percent complete you really are. And that's the that's the bad part, because then all of a sudden you're gonna write down the job at some future date and
your credibility goes down with the the people that look use your statements, the banks, the bonding company that
One thing that you might want to look at there is your trend, right? So if your underbillings were a certain number and now the next time you report the number, those underbillings have gone down by twenty five percent, that's a good thing, right?
Yeah, yeah.
So you know, asking that question, hey, why why were they high and now why are they going down? You know, asking those questions are important.
Makes sense. the next section is the heavy civil CFO playbook. Unit price jobs and AI quantity tracking. Unit price jobs are where heavy civil contractors seem to leave the most money on the table. Frame the problem for the audience. Why is quote unquote I build it just pay me? not how it actually works with NYC agencies.
Part the reason why we spent so much effort on the AI stuff and look and tracking the productivity within the company is is for this reason, right? So we need to capture all the time that was worked on the project.
we get paid on those quantities but unit price right so unit price means that you have a a a a a list of like let's say fifty items on the job that they'll pay you for whether it be maintenance or protection of traffic whether
How many blocks you did in in terms of a you know replacing curb and sidewalk and and building ramps and and that type of thing, because that's the type of work we do. they will use that to pay you, right? So if you're if you're not tracking your quantities daily and at the end of the month you have a discrepancy with
the the owner, the owner you you'd have to sell on whether or not you actually did it. For the most part, if you're not tracking them daily, they're gonna use their quantity and that's gonna be it. You have no argument. Right? But
If you track the the quantity daily and you have a difference, you're you're basically negotiating the difference and you can say, all right, so today I did this, yesterday I did that, the day before I did that, and they can marry up what they're trapping you on. So they might have a difference in in one day, and then you can prove to them that here's where the difference is and this is why you should pay me. And then you'll get your money. But once you
Once you don't good records and once once you give that quantity up, you never get it back. You if you have a difference that you you guys, you know, the owner, the the agency and and us, we agree that that there's a difference, we'll carry that difference until the end, knowing that that'll get resolved. You know.
Because eventually you you do a certain number of blocks, you do a certain number of quantity, that type of thing. So it's important that you we have good records. And those records using the AI tool that we're doing it has provided us an ability to not lose quantity based on like a negotiation or the owner just saying, No, this is all you You get my point.
Yeah, yeah. very
well said.
So also with with the unit price stuff and and obviously estimate this there's two parts to this. you you you have to know your scope with them. And if they ask you to to cut something two inches as opposed to one, no well the contract says one.
So we you have to pay us a change. So it's important that you know that and not and and be able to say, listen, here here in the contract that says this. And we use AI on the contract too. We can look up any contract, type in a phrase and find it. Right? So we're able to know our contract really well, not flip through pages and pages of stuff and and the specs on these contracts are five, six hundred pages long.
Yeah, yeah.
That's one thing. But secondly, when you bid the work, it's important to know that how you're gonna build a job because if you if you know you because they they have limits to the quantity, right? So you have a bid quantity and then if you know you're gonna go over on the quantity, they only allow you twenty-five percent
overage where they pay you at that rate. If you're gonna do more than that, you're gonna have to negotiate a change where you know you'll you'll get a rate close to that maybe, or it'll be signific it'll be a little lower because they never give you more. But the point is to know the quantities that you're gonna do more of out of the contract and and make sure that you negotiate yourself favorably that
when when the change comes, you get paid the proper value. Cause if you bid too high on that item and it costs you more money than what you get paid for it and you have to do more of it, that's when you get killed. So it's important to know how you're gonna bid the job, how you're gonna how you're gonna build the job so when you bid it, you bid it right.
Yeah.
You told me Restani is using AI for daily quality tracking and your exact phrase was that you want your numbers to be quote unquote bulletproof when an agency pushes back. Walk us through how that workflow actually runs, who's capturing what in the in the field, and how does it flow up to billing and reconciliation.
Sure. I was just speaking of of that, but I didn't really tell you how we do it. So in the field, you have your foreman and you have your crews working, and the foreman you know gathers the time and the quantities that were done that day, and they report them up to the the project manager who records them in in HCSS, right?
So he's tracking these items daily and then we use the AI tool to to do the calculations of how we're doing that day. And we'll look plus minus to see how how we did for the day. And then you know, the our COO asks questions as well as the owners and say, Hey, how come we didn't how come we didn't make money today? Or how how come this crew didn't make the target for the day? Or that type of thing. So
Looking at this real time, the the the owners and the COO ask the proper questions to challenge that data, right? So we'll make sure we have the proper data so when we deal with the agency, we have the exact numbers we're supposed to have. So like I said, it makes us it makes us bulletproof with them to make sure we don't lose quantity like I mentioned before. so
The like I said, the the quantities are are derived at the field man level and go all the way up that like I can look at a job and see what we did for the day. So that information
nice.
is like and and I don't go to the field practically all at all, but I can tell you how jobs are doing daily because I can see it on my my
Hm, nice, nice. Right.
That stuff's great. You know.
And what we do with the cost reporting, which is kind of cool, is we can extrapolate how we've done like for instance, when I have my meetings next week, I can we haven't closed the month of September yet. Right? We close the month of
Mm-hmm.
August. But September will probably close the fifteenth of months, let's say. But
Mm.
will know how we're doing through October 2nd when I look at this because I'll be able to use the quantities that are not posted in Sage yet, but to be able to to to know how we've done from the last time we've reported quantities and and the last time we closed the books for for the month of August.
Wow. You also mentioned this could evolve into standalone software, an independent backbone that doesn't lean on Sage 300. Where is that going and what would it unlock for the rest of the heavy civil world if it gets there?
Well,
one thing that you know initially it was something, you know, a grandmaster plan for for that to create your own software doing this kind of thing, but it it it's definitely years away i in in my viewpoint because we're still you know, it's in its infancy with how we're using it and we don't we we gotta get it right within our company first and how we're tracking stuff. And
It's it's a grandiose plan that maybe it can happen five years from now, let's say. But but a lot this you know, the the software companies that do this stuff, Sage three hundred and and and heavy bid and HCSS, you know, Procore, all they
They've been doing this for years. It's not something that can happen overnight. Although I do think that they're probably reacting to using AI and developing their product even further, which if we were trying to catch up to them, we'd even be further behind, right? So ultimately that's a grandiose plan and and it would it would be nice if we could make it happen, but I could tell you that there's a lot of software that you know, you do the demo, you go to like a
CFMA conference and and then it looks great but then when they they show you the demo with your own data it doesn't work. So it's like all right well you know they they have their own problems too so I I think we're a long way away from that but it's it's a nice plan.
Yeah, yeah. Yeah, thank you. The next section is retention, mobilization and cash flow. This one floored me. Substituting open market bonds for cash retention and pocketing the interest income. You put the math at roughly two hundred thousand dollars a year.
On a $5 million retention position. Break down the mechanics. How does the deal actually get structured? And what does it take to get an agency to accept bonds in lieu of cash?
Well, the city agencies have done this for years. and it's like a they they don't advertise it per se because because there's more work for them to do. But ultimately retainage, the purpose of it is to make sure you you complete the work, right? So they don't give you all your money. They give you it used to be ninety percent they would give you a whole ten, but now it's five. That's what the law is in New York. So
They hold five percent retainage. so every dollar you you submit you get ninety five cents back. And then they hold it for a period of time until substantial completion and then they'll release a little of it, and then when you finally complete, they'll release the rest over a period of time. But anyway, retention is just collateral, right? So they they the city agencies allow you to substitute c collateral, like you could put up a bond instead.
for in s and then they'll pay you back the the other five percent as long as they have something that's pledged to them that that enables them to to know that you're not gonna walk off the job. So the guy who's his name is Andy Bodner. He's works at Double Diamond. He's been doing this over thirty years. when I first started doing this with him, we were doing a
city contract when I work at NAP construction in nineteen ninety something. we he he knows the ins and outs of what they need and and we're presently engaged in in in starting that on
one of our large projects where for instance if you put up a bond you and sta and you get back your your money that that bond's gonna have an interest rate it's gonna pay four or five percent whatever whatever the market bears and let's say that you you have
five million dollars worth of retainage you have s have to substitute. If you're getting four or five percent on it, that over a year that's two hundred thousand or two hundred fifty thousand in interest income, that's yours once once they allow the bond to come back and you'll be able to claim it. So it's it's a big number. I mean, you know, if you're doing a a hundred million dollar job, that's five million dollars in retainage at the end. You know? So anyway
It's been it it it's it's hidden profit that you you can take advantage of.
Yeah, very interesting. NYC agencies dangle 5% mobilization payments to drive bids down, and you flagged that as a trap. Thin margins where small errors swing big losses. How should a CFO think about pricing a heavy civil bid when mobilization is in the mix?
Well I think depending on the cash position of your company, they can see an a a a company might bid on a project where they know they're getting five percent up front as a bit of like a panacea for for their present cash flow. And then they'll they'll say, I'll work this out later in terms of let let's say they did the job at at five percent, right?
Margins are really tight now. I'm not sure five percent is we is it I th it might be too low, but let's say five percent for what you say, and you're getting five percent mobilization payment up front. Basically they're paying you your profit up front, right? And if done right, you will have that money and you'll balance out whatever you bill them, you you pay the subs and and and and your costs, and you keep that five percent the whole time, right? So
Good for cash flow, right? If your cash flow is is bad, where you can use that five percent to make up for shortfalls. Sometimes companies will do that. And you can continue to do that by getting another job and getting the next five percent, and almost like a a pyramid scheme. But the the issue is that if you're bidding the job too low as it is,
you're subjecting yourself to, hey, if one thing goes wrong, you can lose that profit. Right? And it it becomes like a little bit of a trap. You might you might take a chance on a risky job because you know you're getting this money up front. You know? and and you the the the market's tough enough as it is. I think that you're gonna have people bidding on work purely for for cash flow purposes as opposed to
being able to do the the job for the right price and and and that's just bad for the industry altogether because you're basically driving everyone to the bottom.
yeah, yeah. Like yeah, race to the bottom. On cash flow
More broadly, you let out a clear hierarchy. Chase DSO hard, negotiate early pay discounts with vendors, and never touch factoring or short-term debt at 20 to 30% plus. You called it an inescapable trap. For a CFO at Heavy Civil Shop that's tight on cash today, what's the right order of operations?
Well, like like I mentioned, you know, taking money, borrowing money at at a higher rate than what your jobs are making is is r a recipe for disaster.
because you're paying that in interest and your your profits aren't guaranteed so you you know the money's going out and and it becomes it's not sustainable. So you know borrowing money for a short period of time it is fine to to get you through, but you have to have a plan before you even do it, right?
And you have to shop that out and and see if you can get a better rate, use collateral to borrow against, that type of thing. It's really
Don't take these hard loans at at a at a high rate just because you need the money tomorrow, you know? Which means you got a cash plan better. You're gonna make sure it's not a crisis when you need this money. So that that stuff's really crucial, right? So doing doing the 13-week cash flow and then managing your cash where you're not paying people before you get paid.
And and spreading the wealth, so to speak, where you have a you owe money to subs below and you're not paying them before you get paid, or if you can string them out even longer, it's in it's important to do that because the less money you borrow, the better you are in the end. And if you can, you know, have them take on some of that burden as well, you won you won't.
especially because as long as you're as long as you're honest in and and
fourth forthcoming with them, hey, I'm gonna pay you X date. we work with subs all the time that we're behind the payments, that we agree to like payment plans and that type of thing. As long as we stick to the payment plans, they're okay. You know, so managing your relationships is so crucial. You know, and they're the relationships are codependent, right? So the the owner is depending on us to build the job.
The subs are depending on us to pay them. And we're depending on the subs to do the work, right? So it's all kind of quid pro quo. We're all the same boat together. So it you if if everyone is just honest about their relationships and how they're gonna take care of their obligations, then then it you can make sure it works out.
So your company, Rastani, you guys are G C, right? So you don't have any field labors yourselves, you're just hiring subcontractors.
We we have
we have over two hundred union people. Yeah, we we
okay. Ma
we have agreements with like seven or eight different unions. So we we make union payments, the payroll weekly is union and you know obviously we have administrative people too but but any any tradesman is a union person.
okay. So there are subs and then they're your own employees too. Right? Both of them are type of
Yes, yes. Yeah,
we have we have subs for stuff that we we might not do, you know, or or they can do it cheaper, you know, 'cause
Yeah yeah.
they might might have an expertise at it. But a
Yeah, yeah.
lot of our a lot of our cost is materials,
But you know, we we do have subs that we pay. You know, certain certain
trades. Like for instance, we're we're the prime prime on a job, you know, we don't really do electrical, so we'll have an electrical sub. Or a plumbing sub or you know, or a steel sub. So th those
Yeah.
kind of things are are things that we don't we're not
That makes sense. The last section, Joe is CFMA, Industry-Wide Issues and Closing.
You've worn just about every CFMA hat. NJ Chapter, President, Webinar Task Force Chair, Conference Planning Chair, Now Executive Board and Education Committee liason. What's the one thing CFMA does better than any other professional org in construction? And what's the one thing you'd change if you had a magic wand?
CFMA has the deepest talent pool for construction experts to draw upon from the terms of expertise on financial subject matter. CFMA really strives to be the go-to for all things construction finance, and we I I think we do a wonderful job at it. The magic wand that I want is making sure the world knows this, right? The
Hm.
secret needs to be let out to everyone in a big way.
being on the executive committee and discussing reach to other organization like ours, such as
That we're in the same boat as them, but our expertise in the construction finance area helps them because we help train them to be better at what they're doing. It's important that we be known as the resource for all construction knowledge, developing and expertise.
need to be marketed better and and and that's that's the truth I mean we we shouldn't be a secret we should be hey you you need you need a construction financial professional go to CFMA and and you know there's a list of them we post a job there you know like all that kind of stuff you know and you need an article written get someone from CFMA to write it you know or do a webinar or do
Or do a presentation, anything, you know, C FMA is the the the source for it.
It's a great organization. We are also part of CFMA.
I do know that.
You raised a real concern in our prep about the benchmarker that contractors submitted data and CPA submitted client data may be getting double counted, which warps the benchmarks the whole industry leans on. Unpack.
That for the audience, why does it matter and what would the fix look like?
Well, the the fix is already there, so to speak,
Look how?
right? So we it you know, talking about the benchmarker, the the source of information is you have companies that that post their own data on in into the benchmarker and you know, they pay for the information, the comparative and and and they wanna know how they're doing against industry standards, the the best companies, the middle companies and
Lower 25%. That information comes from them, but CPA firms are doing their you know their books, and they're using that information as well and giving it to CFMA as part of an overall package. So the CF the CPA firms
you know, disclosing to the gatherers, hey, we use these firms data, it's all together, you know, so they're not giving away the individual data to on you know, without them knowing per se, but that information is all t all together in a pool of let's say twenty contractors. So when they give that information and if we counted
that one contractor that did it themselves, you would double count it. But you know, giving giving the benchmarker people that information, they know not to count the the submission on the individual basis because it's already in the number. You get my point?
Because
CPA firms are trying to anonymize their clients, right? So how are they gonna give that information to CFMA?
Well they g they give it is well they have these contractors as part of their their pool of of you know their pool of the the job the contractors they audit. So they'll give they'll say, well these twenty contractors add up to
two billion dollars worth of revenue and this is you know the categories that type of thing so they can translate
Well.
that information they could say these twenty are in it you submitted it already you can pull that information out you say and not double county you know
okay, okay. So the CPA firms agreed to give that information to C FMA?
Yeah, well they they use it because it's good for the industry. They're not disclosing one individual contractor because it's all together. You get my point? Yeah. So they're they're not saying, you know, Restani
Mm. yeah, okay, okay. So i i i the submission is is still yeah.
did X amount of revenue this year and this amount
Yeah yeah.
of profit and and this is what their ratios were and stuff like that. It's all embedded into like a combined
okay.
though. and really that's the that's the best way to get a lot of data. Because otherwise if you if you're counting on like each individual contractor to do it themselves, i it it's you're not gonna get enough data that matters. You know?
Yeah, yeah. I mean y you need
the CPA firms, like the contractors they're so busy, you know, to to do this work.
Yeah, and and and they have all this
information at their fingertips, right? So it's all just
Yeah.
combining it and saying, all right, this is what the group did this year. W and and you're not disclosing any one contractor for what it is. You know what I mean? You just say this it's
Yeah, makes sense. Yeah, definitely.
this pool of these contractors.
Definitely. Last one. Close us out with the pitch. For a first year construction CFO listening to this, what's the one thing you would tell them to do this month? And feel free to make the pitch for CFMA, the N J Chapter, or anything else you want the audience to check out. You warned it.
First, always monitor cash closely at all times. Know what's going through your books, even your credit cards and all that other stuff. Know where you are and and and do bank-to-book reconciliations constantly and monitor your credit lines. Obviously avoid large interest rate loans always. You do a monthly close because
y and and as close to the end of the month as possible because then the data doesn't get stale and you can react to it and and the people who matter, the the owners of your company and and and the COOs and the CFOs can react and and dictate policy to fix stuff that's going wrong. It's and
also holding people accountable for what's going wrong or or what they're doing right and let's do more of it, you know. doing estimate the completes on your project monthly because then you see the trending and and you can react to any changes. I know it seems like a pain, but once you do and you have a framework, it's all just monitoring changes. Alright? So
Mm.
that's
But i it's painful to do it right the first time and then after that to monitor the changes is not so bad. along with the same you you build out your WIP schedule that way from doing estimates to complete, taking your billings, taking your revenue recognition, your profitability, that type of thing. you gotta verify your WIP monthly and focus on under billings and why you're under billing. So
those those items are important because you you might be masking job problems that will come home the roots later. I do a few things personally that when I was younger in my career I I said, I I don't know why I have to do this, but the more I did it, the more I realized it was really important. I have weekly staff meetings, right? And
Yeah, those meetings those meetings are like a half hour. They started like they used to be an hour. Like a half hour we have a preset agenda we go through. But but it's really important because the
The staff has to know that they might be asked questions about what they're doing, what they're working on, and and and just to be accountable for the work that they they said, I'll get this done this week, and then if I ask about it and it's not done, you know, it just it's important to keep accountability for everybody. And even myself, because I have to build the agenda and and and ask the questions and and and do the right thing as a
Multi job being the same same situation. It's like you want to have the project managers come to the meeting, know exactly what's going on with their projects, be able to ask answer any question, make sure they have the right contract value, the the right estimate to complete, what's going wrong, how you know, raise raise issues where they're not getting the help they need. The communication is so important. And it holds them accountable and holds us accountable to make sure we're asking the right questions as well.
I mean listen, no one likes meanings that people think, meaning is a waste of time. No, it it isn't. Too many meetings are a waste of time, but some key meetings have to happen. You know. some of the things I learned from from this I learned, you know, best practices from from my long membership in C FMA and doing this kind of stuff and how important these things are. having having the resource to to bounce stuff off of and and
long time friends that I can ask questions of how do you handle this and and
is important to have. It's the it's the best resource for anything you don't know. And because someone in your network probably does know. And
Yeah.
lastly I'll close with about CFMA, you know, obviously I'm a huge fan. they they say you you come for the education but you stay for the friendship and the networking.
Mm.
Joseph, this was phenomenal. always love to see your smiling face. And I had a great time spending time with you in CFMA National.
Yeah,
no, it was it was fun. I mean and and the group we're part of, that community group, is really great.
Definitely. Joseph, thank you for coming on to the show.
Well, thanks for having me. I I've seen a lot of these and I'm I'm impressed with what you do. Thanks for doing
Subscribe to our newsletter
New Finance at the Jobsite episodes and behind-the-scenes updates, straight to your inbox.
More episodes
All episodes →
63 minEric Pratt & RishiThe Printer in the CFO's Living Room: How Construction Really Buys AP Tech — Eric PrattListen now
36 minBrandon Keyes & RishiThe $80,000 Engine: What Equipment Dealers Know About Contractor Operations — Brandon KeyesListen now
55 minCaryl Coronis & RishiFrom 15 Attendees to 300: How Caryl Coronis Rebuilt the CFMA Lone Star ConferenceListen now